August 2022

Couple of photos from the current situation on the construction site

June 2022

The construction of House I FAZE is proceeding according to plan.

April 2022

The construction of the Reservoir and water treatment plant is in progress.

March 2022

Rough construction completed. Windows assembly and installation are in progress

January 2022

At the Ceremonial Announcement of the Real Estate Project of the Year 2021 competition, we won the Expert Jury Prize for the best project in the Central Bohemian Region.

January 2022

Construction of the houses 1 phase continues

December 2021

As long as the weather allows, the construction of the Houses runs at full speed.

November 2021

The construction of the basic passports, of the gas pipeline and water supply system continues.

September 2021

We entrusted the construction of the NOVA KVETNICE PROJECT, STAGE I, PHASE I to the company BAUSTAV a.s. , which has been operating on the construction market for about 30 years and has dozens of successfully completed residential buildings.
Commencement of construction - September 2021.
More about the company at www.baustav.cz

August 2021

The construction of engineering networks continues

July 2021

Construction of water supply and sewerage has begun

May 2021

The Decision on the change of the building permit for the construction of family houses - STAGE I came into force

April 2021

MANABAU s.r.o. won the tender for the contractor of engineering networks and communications of the I STAGE NOVÁ KVĚTNICE project.

It is a czech company, financially stable and dynamically developing, which was established in 2014 by a group of experts from construction companies from the ranks of managers and manual professions with more than 25 years of experience in the field.
www.manabau.cz

March 2021

For the Technical Supervision of the Investor and the Health and Safety Coordinator was chosen Mr. Jozef Černý, STAVBYADOZORY s.r.o. Mr. Černý has been operating on the construction market since 1993 and has completed hundreds of successful constructions and reconstructions.

February 2021

We started selling the first phase of the project, cooperation with LEXXUS / Savills

January 2021

Project web site.

December 2020

Tree felling.

info@novakvetnice.cz 608 444 701